What a scope is for
A written scope is the page both sides check when they disagree. It says what will be built, how you'll know it's finished, and what it costs.
A good one is short enough to read in one sitting. For most first versions, that's about 2 pages.
Start with the job, in your words
Open with who will use the software and what they do today. One paragraph is enough.
Take "Our 6 staff take bookings by phone and copy them into a sheet." That line tells a builder more than a feature list.
Describe what people can do
List what each kind of user can do, one line each. Write them as sentences with a person in them.
"A manager can refund an order up to $500" is clear. "Refund module" leaves the limit, the person and the approval to guesswork.
Give each line the rule that makes it hard. Who may do it, up to what amount, and what happens next?
Say what "done" means
For the lines that matter most, add a worked case. Given this input, the software should give this result.
For example, a refund over $500 goes to the owner for approval. The builder tests against these cases, and you check them at handover.
Add the things that aren't features. The software runs in your accounts, a staging copy exists, and a backup has been restored once.
Scrum teams call this a "definition of done". It's a shared description of what finished work must meet.
Write down what's left out
A fixed price covers only what's written. Anything both sides merely assumed becomes a dispute later.
Common items to list as out of scope:
- mobile apps, if the first version is a web page
- moving old records from the current system
- languages beyond the first one
- connections to other systems you haven't named
- reports beyond the ones listed
An item left out can still be built later. It's priced separately, if and when you want it.
What can stay open
Screen layouts and colours can stay open. They're easier to settle on a working demo.
The technology can stay open too, as long as the scope says where the software will run.
Name what you'll provide
A builder depends on you for some things. List them, so a delay has a clear cause.
Typical items are sample data, access to your accounts and someone who can answer questions. Agree how fast they'll answer, such as within 2 working days.
Price, payment and changes
A fixed price should be one number, with payment dates tied to visible progress. A first demo on your data is a common one.
Say how long the price holds. Plans change, so the scope should also say how a change gets priced.
Any change should be priced in writing before work on it starts.
Who owns what
The scope or the contract should say the code is yours. It should also name the accounts the work happens in.
Your repository and cloud account, in your company's name, are the safest place for it.
When 2 pages isn't enough
Some jobs need more. Software for a regulated field, such as health records or payments, often needs its rules spelled out.
So does work with many outside systems, each with its own quirks. Even then, keep the first 2 pages as a summary anyone can read.
Checklist for the scope you've been sent
- Does it say who uses the software and what they do now?
- Is each feature a sentence with a person and a rule?
- Do the key features have a worked case to test against?
- Is there a list of what's left out?
- Does it say what you must provide, and by when?
- Is there one price, with payment dates and how long it holds?
- Does it say how a change gets priced?
- Does it name the accounts the code and data live in?
If any answer is no, ask for it before you sign.